64 Electrical installation
7 Pull lightly to check that the
contact has properly engaged.
8 Insert the test pin with the
corresponding side into the
socket or plug. If the contact is
properly assembled, the white
marking on the test pin must
still be visible.
9 Screw on the cable gland
hand-tight and then tighten it
to the correct torque for the
solar cables used. Typical
values are 2.5 Nm to 3 Nm.
Description